City Construction Projects

Posted on: June 4, 2018

5339 Grant Bus Shelters - 2018

PW Logo 2

The timeline for this project is from July to September.  


Project Update:

The project is scheduled to begin on 8/15/18.  Work will include the installation of one 12' x 18' bike shelter, two 5' x 14' bus shelters, three 5' x 10' bus shelters, one 6' bench, concrete pads and accessories at various locations throughout Moscow. 

There will be sidewalk and shoulder closures throughout construction.  The initial shoulder and sidewalk closures will be on Mountain View (at D Street) and East F Street (at Orchard).

For maps click on Mountain View and F Street

All lanes and directions will remain open.

For questions or concerns, please contact City of Moscow Engineering at 208-883-7034