This project’s scope includes construction of approximately 3079 linear ft of 24” C900-16 water main, 292 additional linear ft of various size C900 water main, as well as surface restoration of parking lots, highway, street, sidewalks, and green strips. Construction of water main includes new hydrants, associated fittings/valves, thrust restraint, and connection to existing water mains.
Substantial completion for this project is scheduled for Fall 2023.
ADA accessibility is a top priority for the City in all projects. If this project, or any other City project is found to be impacting anyone's ability to access public services, please email ejaccessibility@ci.moscow.id.us or call 208-883-7600.
Every effort is made to adhere to the project schedule; however unforeseen circumstances may require adjustment. For questions about this project, including the project schedule or concerns about resident access, contact City of Moscow Engineering Division.