Idaho Transportation Department (ITD) will be carrying out a Concrete Grinding Project on Jackson Street (US 95) between W. C Street and Eighth Street, in Moscow, beginning on June 25th and continuing through mid-August.

ITD’s contractor for this project is Acme Concrete Paving, Inc., of Spokane.  Acme will use a concrete pavement rehabilitation technique to grind and repair concrete slabs on Jackson Street and reseal the joints.


NEW UPDATE FROM ITD:

  • The contractor has finished all grinding operations and replaced 39 concrete panels on Jackson Street; crews have moved onto sealing joints and cracks.
  • Project is on schedule to be completed by August 17, before University of Idaho starts the next semester.