UPDATE: Mountain View paving from Sixth Street to Joseph Street is now COMPLETE and open to all traffic!
Thanks to Motley-Motley, Inc., for some speedy paving! Check out the attached picture to see the finished product!
Project Description:
The improvements consisted of an asphalt grind and inlay. During this process the road surface is milled to a smooth plane, removing the existing asphalt to a depth of approximately 2.5 inches. New asphalt is then applied, providing a sealed road surface. This method is intended to repair roads with severely damaged surface layers while allowing the City to keep the structurally sound base layer. A grind and inlay project is done for a fraction of the price of a full road rebuild but still results in a smooth road surface and increased roadway life.